At Skipper Limited, Transmission Towers are viewed not just as a Product, but as a Service. From designing and assembling each component to the delivery of a customized product, Skipper is present along the entire value chain.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Power Grid Corporation of India Limited. Saudamini "Plot No-2, Sector-29,Gurgoan-122 Haryana | Tower Package -TW 09 for 800kV HVDC Raigarh- Pugalur Transmission Line, Part- IX | 85.45 KM | 800 | Tamil Nadu | - | 07.06.2020 | 36 |
The package was part of a 1800km line originating from Raigarh in the State of Chattisgarh and terminating at Pugalur in the State of Tamil Nadu, transmitting 6000MW power. The line was the 1st HVDC transmission project executed by Skipper under POWERGRID.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Power Grid Corporation of India Limited. Saudamini "Plot No-2, Sector-29,Gurgoan-122 Haryana | Supply, Erection, Civil, Testing and commissioning of equipment for construction of 765kV HEXA ZEBRA Conductor Transmission Line from Fatehgarh (II)- Bhadla (II) for PGCIL under TBCB package | 189.00 KM | 765 | Rajasthan | - | Schedule in April 2021 | 21 |
First TBCB (Tariff Based Competitive Bidding) project for the organization. Also the first 765kV D/C (H) transmission line order received by Skipper under POWERGRID of value 525cr. Overcoming strict lockdowns and severe COVID crisis during most part of year 2020, Skipper successfully completed the job well in time, credit to the superior management and site team during the entire duration of 19 months.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Power Grid Corporation of India Limited. Saudamini "Plot No-2, Sector-29,Gurgoan-122 Haryana | 400 kV D/C (QUAD) JIGMELING - ALIPURDUAR Transmission Line (ASSAM PORTION) | 110.00 KM | 400 | Assam-West Bengal | - | 27.03.2021 | 60 |
Due to prolonged monsoon period, working season remained minimum (5-6 months only) every year. Also underground water table being high, almost every location needed dewatering before and during the concreting work. In addition, local issues incl. extortion calls remained prominent during the entire course of the project resulting in major interruptions in daily work flow. Also Skipper, although being the other partner of the JV, took to execution of portion left by the lead partner after the later went bankrupt. The entire line was passing through forest corridor covering 43% of line length.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Rajasthan Rajya Vidyut Prasaran Nigam Limited Vidyut Bhawan Janpath Jyoti Nagar Jaipur-302005 | Construction of LlLO of one circuit of 400kV D/C Akal- Jodhpur (New) (Quad Moose) Line at Jaisalmer-2 | 10.00 KM | 400 | Rajasthan | KFW Funding | 29.10.2020 | 15 |
The transmission line was passing through remote areas of Jaisalmer district prone to severe sand-dunes and high intensity winds all along the day. Also during construction activities, severe obstructions from local people with the issue of different compensation policy in between Private TL lines and State Government Lines and frequent incidents of theft, hampered site activities on regular basis. The line was essential to feed the newly built Jaisalmer (2) S/S and utilize the power travelling from Akal S/S to Jodhpur.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Power Grid Corporation of India Limited. SR 2- Bangalore RHQ | Re-Alignment work of 400kV D/C Multi Circuit Transmission Line in Yelahanka Presidency University for PGCIL | 1.20 KM | 400 | Karnataka | - | Schedule in June 2021 | 24 |
The diverted line was passing through The Presidency University boundary in Bangalore city. In order to avoid any future congestion due to continuous expansion of the University and to ensure uninterrupted power supply, POWERGRID a Govt. of India enterprise took to the diversion work outside the University boundary.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Rajasthan Rajya Vidyut Prasaran Nigam Limited Vidyut Bhawan Janpath Jyoti Nagar Jaipur-302005 | Construction of 13kKV Chhatargarh-Loonkaransar D/C Transmission Line on Turnkey Basis | 70.85 KM | 132 | Rajasthan | KFW funding | 27.07.2020 | 25 |
The area was prone to frequent sand dunes and strong winds causing loosening of soil resulting in total collapse of excavated pits. Also to include the extreme climatic conditions during the summer days causing serious trouble to working manpower.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Rajasthan Rajya Vidyut Prasaran Nigam Limited Vidyut Bhawan Janpath Jyoti Nagar Jaipur-302005 | 220 kV D/C AKAL - JAISALMER 2 TRANSMISSION LINE | 56.00 KM | 220 | Rajasthan | KFW funding | 01.03.2020 | 31 |
The transmission line was passing through areas of Jaisalmer district prone to severe sand-dunes and high intensity winds all along the day. Also during construction activities, severe obstructions from local people with the issue of different compensation policy in between Private TL lines and State Government Lines and frequent incidents of theft, hampered site activities on regular basis.
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Haryana Vidyut Prasaran Nigam Limited Sakti Bhawan Panchkula | 220 kV & 132 kV TRANSMISSION LINES IN KAITHAL AREA | 80.20 KM | 132 | Haryana | - | 16.01.2021 | 32 |
This project marked our first presence in the State of Haryana. Main challenges include land being costly and highly productive, resistance from local people became prominent resulting in frequent work stoppage and continious involvement of local administration for day to day activities to complete the lines. Maximum of the land occupied round the year for agriculture works.
220 kV D/C Palampur - Hamirpur Transmission Line
Name of the company for which work was executed | Details of works executed on Turn key basis | Approx. route length of Transmission Line | Voltage kV | Location of work executed | Name of Funding Agency (if any) | Date of work completion | No of months taken for work completion |
---|---|---|---|---|---|---|---|
Himachal Pradesh Power Transmission Corporation Limited Shimla | 220 kV D/C PALAMPUR - HAMIRPUR TRANSMISSION LINE | 57.00 KM | 220 | Himachal | KFW funding | Schedule in May 2021 | 37 |
More Than 75% of the entire line passes through the hilly terrains including steep slopes and deep valleys. All the construction materials head-loaded to every site by manually and with the help of Mules. Encountering of hard rock strata in almost 80% locations during excavation, Unseasonal rain fall throughout the year and extreme cold weather situation during winters was a big challenge in the construction of line.
Name of the company for which the work was executed | Project Name | Voltage Rating | Qty. Supplied (MT) | Supply Completion Month |
---|---|---|---|---|
Power Grid Corporation of India Ltd. (PGCIL) | Tower Package TW04 for Pugalur HVDC Station - Thiruvalam 400 kV (Quad) D/C line (PART-II) associated with HVDC Bipole link between Western Region (Raigarh, hhattisgarh) and Southern Region (Pugalur, Tamil Nadu- North Trichur (Kerala) & AC System Strengthening at Pugalur end | 400 kV | 18707.883 | Jan'21 |
Power Grid Corporation of India Ltd. (PGCIL) | TW 03 Package of 400 kV (Quad) D/C Line (Part-I) associated with HVDC Bipole link between Western region (Raigarh, Chattisgarh) and Southern region (Pugalur, Tamilnadu) - North Trichur (Kerala) & AC System Strengthening at Pugulur end. | 400 kV | 13389.302 | Nov'20 |
Power Grid Corporation of India Ltd. (PGCIL) | Manufacturing, Inspection, Testing, Packing and Forwarding, Supply of Galvanized MS & HT Tower for Sterlite (Package-1) 400 kV D/C Silchar-Missa Transmission Line | 132 & 400 kV | 16662.124 | Oct'20 |
Power Grid Corporation of India Ltd. (PGCIL) | Transmission Line Package TL01 for Transmission Lines (a) Sitamarhi (New) Motihari 400 kV D/C (Triple Snowbird), (b) Darbhanga-Sitamarhi (new) 400 Kv D/C (Triple Snowbird) (c) LILO of Kishanganj-Patna 400 kV D/C (Quad Moose) line of PGCIL at Saharsa (New), (d) LILO of Both Circuits of Nabhinagar-II Gaya 400 kV D/C (Quad Moose) line of PGCIL at Chandauti (New) associated with Transmission Project System namely "ERSS-XXI" under Tariff Base Competitive Bidding (TBCB) Route | 400 kV | 15867.103 | Sep'20 |
Name of the company for which the work was was executed | Type | Details | Heightin Mtr | Highlight |
---|---|---|---|---|
Power Grid Corporation Of India Limited (PGCIL) | 400kV - Monopole | DC Quad Moose | 38.63 | Designed, Manufactured and Tested - Only company in India to do so |
Power Grid Corporation Of India Limited (PGCIL) | 765kV - Monopole | PD/PE+0M Ext (0-60d)/DE | 42.19 | Designed, Manufactured and Tested - Only company in India to do so |
Modern Rail Coach Factory in Rae Bareilly, UP | - | Pole - Flag Mast | - | Tallest in the country |
"Skipper is one of our most dependable tower partners and we look forward to our association growing from strength to strength."
S.C. Jha"Over the past six years, Skipper has supplied 400 KV and 765 KV Transmission Towers to 7 of EMC's transmission projects. Their quality and commitment is quite good and we wish to take them as our preferred supplier in future also."
RK Shah"We are happy to have Skipper as a JV partner in 4 major Transmission Projects. Their product quality is excellent and their approach is highly professional and ethical."
BS Gill"Skipper has been a Ramboll Manufacturing partner for more than 6 years and we have found them to be a fair and transparent Organization. We wish them all the best in their future endeavours."
Trond M. Bredesen"Congratulations Skipper for successfully executing supplies for the difficult Multi-Circuit Towers (average tower weight more than 60 MT) to our Gaya-Kodarma T/L Project. We've found Skipper to be a reliable and quality-conscious manufacturer and look forward to working with them again."
Santosh Thakur